Two-tier CI phase 2: promote sf-e2e to a PR smoke gate

Phase 2 of PLAN-two-tier-ci.md. Flips .github/workflows/sf-e2e-functional.yml to also run on pull_request, superseding the phase 9 "dispatch/schedule only" caveat (decision 4 in PLAN-kerbside-vdi-tokens-phase-09-e2e.md).

Prompt

"Please do the cleanup and then plan and implement phase 2 -- I think the promotion precondition in hindsight is too harsh given the experimental nature of kerbside as a project and my generally underspeced CI cluster."

Situation

Phase 9 decision 4 gated the sf-e2e lane on workflow_dispatch and a nightly schedule only, "until it is shown stable", with an explicit intent to promote it to a PR gate "once green and reliable". The master plan's open question 1 proposed a promotion criterion of ten consecutive green scheduled runs, consistently under ~30 minutes.

The run history as of 2026-08-08 (nightlies unless noted):

Date (UTC) Result Duration Cause of failure
2026-08-08 queued for hours - runner pool contention
2026-08-07 success 16.9m
2026-08-06 success 29.1m
2026-08-05 success 16.2m
2026-08-04 success 35.1m
2026-08-03 failure 11.3m kerbside-proxy compile break (tonic Body mismatch) in the proxy-wheel build
2026-08-02 failure 11.2m same compile break
2026-08-01 success 16.2m
2026-07-31 failure (sched), success (dispatch) 19.9m / 46.9m happy-path driver, during bring-up

The relaxed promotion criterion

Maintainer decision (2026-08-08): the N=10 criterion was too harsh in hindsight, for three reasons.

  1. Kerbside is experimental. The cost of a false-negative PR gate is a re-run, not a blocked release train. The bar for "trusted enough to gate PRs" should reflect that.
  2. The CI cluster is underspecced. Nightly-only signal accumulates one data point per day at best — the 2026-08-08 nightly sat queued for hours behind other work — so ten consecutive greens is weeks of calendar time for little extra confidence.
  3. The lane fails for the right reasons. Every failure since bring-up completed has been a real kerbside defect (the 2026-08-02/03 runs caught a kerbside-proxy compile break against a dependency bump — exactly the class of breakage a PR gate would have stopped before merge), not lane flake. Four consecutive green nightlies (2026-08-04..07, 16–35 minutes) since that fix is sufficient evidence the lane itself is sound.

Promotion on this evidence, rather than after ten greens, is the decision this plan records.

Mission

Make the sf-e2e lane a pull_request smoke gate without weakening anything else: keep the nightly schedule and manual dispatch, protect the underspecced runner pool from stacked superseded runs, and skip review-only changes the lane cannot exercise.

Execution

One commit, this branch (sf-e2e-pr-promotion):

  1. .github/workflows/sf-e2e-functional.yml
  2. Add a pull_request trigger (branches: develop) with the same review-only paths-ignore list the direct-qemu and functional-tests workflows use — keep the three lists in sync.
  3. Add a job-level concurrency group (${{ github.workflow }}-${{ github.ref }}, cancel-in-progress: true), matching the style of the functional-tests matrix jobs, so a superseded push cancels the running lane instead of queueing another 120-minute-timeout job on the l pool.
  4. Replace the phase 9 header caveat with a comment recording the promotion and why the schedule survives it: build-smoke-cluster deploys Shaken Fist at develop HEAD, which moves independently of kerbside PRs, so the nightly catches SF-side drift no kerbside PR would surface.
  5. No other behaviour changes. The environment-retention step is already guarded by github.event_name == 'workflow_dispatch', so the empty inputs.retention on PR runs is inert.
  6. Statements that become false (minimal fixes only; the wider documentation consolidation is phase 4):
  7. AGENTS.md: the sf-e2e section's "dispatch- and nightly-scheduled, NOT a PR gate — phase 9 decision 4".
  8. README.md: the "dispatch- and nightly-scheduled" parenthetical in the sf-e2e paragraph.
  9. PLAN-kerbside-vdi-tokens-phase-09-e2e.md: annotate decision 4 as superseded (do not rewrite the historical decision).
  10. PLAN-two-tier-ci.md: mark the precondition resolved, record the relaxed criterion under open question 1, and set phase 2 to Complete in the execution table.

Risks considered

  • Runner pool load. This adds a ~17–35 minute l-runner job to every non-review-only PR push, and renovate PRs are the bulk of PR volume. Mitigations: the concurrency group cancels superseded runs; review-only PRs skip entirely; and the direct-qemu lane already set the precedent of an l VM job on every PR. If the pool saturates in practice, the fallback is demotion back to schedule-only (the same escape hatch open question 2 records for the oVirt lane), not a weaker assertion set.
  • Fork PRs on self-hosted runners. pull_request on self-hosted runners runs PR code on the pool. This is the repository's existing posture — direct-qemu and functional-tests already do it, gated by GitHub's approval-for-outside-contributor settings — so this change adds no new exposure class, only one more workflow inside it.
  • Required-check status. Adding the trigger makes the lane run and report on PRs; making it a required check is manual branch protection work, deliberately deferred to phase 3 alongside the merge-queue re-wiring. Until then a red sf-e2e is visible but advisory.

Out of scope

  • Branch protection / required checks / merge queue: phase 3.
  • docs/testing.md, .claude/CLAUDE.md's CI workflow list (which predates this and does not list sf-e2e-functional.yml at all), and the broader AGENTS.md / ARCHITECTURE.md pass: phase 4.

Back brief

Implemented 2026-08-08 as planned. The first pull_request run of the lane is the PR that carries this plan — treat that run as the promotion's own smoke test.