Skip to content

Proxy dev releases phase 3: the contract handshake

Master plan: PLAN-proxy-dev-releases.md. This phase embeds a sha256 of kerbside/rpc/kerbside.proto in both the Python package (a committed constant written by tools/gen-protos.sh) and the Rust binary (a build.rs compile-time env), and makes the daemon compare them before launching the proxy — refusing with a remediation-listing message on mismatch. This is the backstop that makes sparse dev-wheel publishing safe: any skew the phase 1 path filter lets through (or the merge-to-bootstrap window creates) becomes a loud startup refusal instead of a subtle protocol failure.

Planning effort: high (per the master plan — the change spans the gRPC contract convention, build.rs, clap, and the supervisor launch path across two languages).

Scope

In scope:

  • tools/gen-protos.sh: additionally write kerbside/rpc/contract.py carrying the proto's sha256.
  • kerbside/rpc/contract.py (new, generated, committed) and a unit test pinning it to the actual proto bytes.
  • rust/kerbside-proxy/: sha2 build-dependency, build.rs hash embed, a --contract-hash print-and-exit flag, a unit test.
  • kerbside/proxy_supervisor.py: pre-launch handshake, refusal message, KERBSIDE_SKIP_CONTRACT_CHECK escape hatch, unit tests in kerbside/tests/unit/test_proxy_supervisor.py.
  • End-to-end verification against both the freshly built binary (hashes match) and the released 0.4.0 wheel binary (predates the flag — refusal path), run in the management session.

Out of scope: documentation beyond code comments (phase 4 covers AGENTS.md / ARCHITECTURE.md / docs, and must document the two env vars); the publish workflow and specifier (phases 1-2, done); pruning (phase 5).

What the survey found

Verified against the tree on 2026-08-14. The master plan's phase 3 sketch contains no false claims; the only correction it needed was resolving its "refuses/warns" hedge to "refuses", which open question 1's operator decision already settled. Specifics:

  • tools/gen-protos.sh regenerates the checked-in stubs into kerbside/rpc/ and is invoked as tox -egenprotos (tox.ini:50-58 pins the toolchain for deterministic output). Extending it keeps a single regeneration entrypoint.
  • kerbside/rpc/ contains __init__.py, the proto, the four generated stub files, server.py and servicer.py; a new generated contract.py fits the existing convention of committed generated artifacts.
  • The kerbside wheel does not ship the .proto ([tool.setuptools] packages only, pyproject.toml:132-133), so hashing must happen at generation/build time, not runtime — confirming the master plan's committed-constant approach.
  • rust/kerbside-proxy/build.rs already declares cargo:rerun-if-changed=<proto>, so a compile-time hash embed re-derives whenever the proto changes with no extra plumbing. [build-dependencies] currently carries tonic-prost-build and protoc-bin-vendored (Cargo.toml:90-95); sha2 joins them.
  • main.rs uses derive-style clap (struct Args, main.rs:74+) with long flags only — a --contract-hash bool flag matches the house style. Args::parse() happens at main.rs:133 before logging init, so the flag can print-and-exit cleanly.
  • kerbside/proxy_supervisor.py::launch_rust_proxy() (line ~97) is find_proxy_bin()build_proxy_argv()Popen; the handshake slots between the first and last of those. kerbside/tests/unit/test_proxy_supervisor.py already exists for the new tests.
  • Phase 2's completion was spot-checked (committed floor present and parseable; generalised stamp branch present; tree clean) and its Execution-table status flipped to implemented in this planning commit. origin/develop has not moved since the phase 2 rebase, though PR #307 entered the merge queue during planning — a final rebase before the eventual PR remains on the plan- completion checklist.

Decisions

  1. The contract identity is the sha256 of the proto file's raw bytes, embedded at generation time (Python, committed constant) and compile time (Rust, env!). No canonicalisation or comment-stripping: a comment-only proto edit changes the hash and forces a republish, which is a false positive we accept — proto edits are rare, and canonicalisation code on two sides is its own skew risk. This is the decision a reviewer is most likely to argue with.
  2. sha2 is a build-dependency only on the Rust side — compile-time hashing costs nothing at runtime and avoids entangling the runtime dependency tree (ring/rustls) in hashing duty.
  3. The committed constant is written by gen-protos.sh, not by hand, and a unit test (kerbside/tests/unit/) recomputes the hash from the proto and compares — so a proto edit without regeneration fails tox -epy3 in CI. No new CI job needed.
  4. Refusal semantics (implements the operator's open-question 1 decision): on mismatch, launch_rust_proxy() raises RuntimeError naming BOTH hashes, the binary path, and the remediation options (upgrade the kerbside-proxy wheel; rebuild rust/kerbside-proxy; point KERBSIDE_PROXY_BIN at a matching binary; set KERBSIDE_SKIP_CONTRACT_CHECK=1 to bypass for debugging). A binary that does not understand --contract-hash (every release ≤0.4.0) is treated as a mismatch with tailored wording ("binary predates the contract handshake"). The escape hatch logs a WARNING and launches anyway. Sub-decision most worth flagging: hard-refusing old binaries is deliberate — current-Python-plus-0.4.0-binary is exactly the broken pairing this plan exists to catch, and the escape hatch covers the operator who knows better.
  5. The subprocess probe is bounded: --contract-hash runs with a 10-second timeout and any failure mode (timeout, non-zero exit, garbage output) is a refusal, never a silent pass.
  6. All cargo operations run in the rust Docker image (the operator keeps Rust toolchains off the host); briefs give the exact pattern, mirroring phase 1's step 1d.

Step plan

Step Effort Model Isolation Brief for sub-agent
3a medium sonnet none Extend tools/gen-protos.sh to write kerbside/rpc/contract.py after stub generation: a header comment saying the file is generated by tools/gen-protos.sh (run tox -egenprotos) and must not be hand-edited, then CONTRACT_HASH = '<64-hex sha256 of kerbside.proto>' computed with sha256sum kerbside.proto \| cut -d' ' -f1 (the script already cd's into kerbside/rpc). Run tox -egenprotos; if ANY already-committed generated stub changes beyond the new contract.py, STOP and report the diff rather than committing regeneration noise. Add kerbside/tests/unit/test_contract.py: locate the proto relative to the test file, hashlib.sha256 its bytes, assert equality with kerbside.rpc.contract.CONTRACT_HASH, and assert the constant is 64 lowercase hex chars. Follow repo Python style (single quotes, 120-char lines). tox -epy3 and pre-commit run --files <touched> must pass.
3b high opus none Rust side, all cargo commands via docker run --rm -v /srv/kasm_profiles/mikal/vscode/src/shakenfist:/srv/kasm_profiles/mikal/vscode/src/shakenfist -w <worktree>/rust/kerbside-proxy rust:latest cargo ... (host has no Rust toolchain by policy; the mount path matters because the worktree's gitdir and build.rs's ../../kerbside/rpc both resolve under it). (1) Add sha2 = "0.10" to [build-dependencies] with a comment. (2) In build.rs, after compile_protos, read the proto bytes, compute sha256, and emit cargo:rustc-env=KERBSIDE_CONTRACT_HASH=<hex>. (3) In main.rs, add to struct Args a /// Print the embedded gRPC contract hash and exit. #[arg(long)] contract_hash: bool, and immediately after Args::parse() (before logging init): if set, println!("{}", env!("KERBSIDE_CONTRACT_HASH")); return;. (4) Add a unit test asserting env!("KERBSIDE_CONTRACT_HASH") is 64 chars of lowercase hex. (5) cargo fmt, cargo clippy --all-targets (warnings clean, matching rust.yml's bar), cargo test, and cargo run --release -- --contract-hash must print a 64-hex line; report it and leave target/ alone (gitignored). Set CARGO_TARGET_DIR to a path under /tmp inside the container if root-owned files in the worktree would result — check git status is clean of new files afterwards.
3c high opus none In kerbside/proxy_supervisor.py: add SKIP_CONTRACT_CHECK_ENV = 'KERBSIDE_SKIP_CONTRACT_CHECK'; add get_binary_contract_hash(bin_path) running [bin_path, '--contract-hash'] via subprocess.run with capture_output=True, text=True, timeout=10, returning the stripped stdout on rc==0, or None on any failure (non-zero rc, timeout, empty/malformed output — 64 lowercase hex or bust); add check_contract(bin_path) comparing against kerbside.rpc.contract.CONTRACT_HASH and raising RuntimeError per plan decision 4 (message must name both hashes — or "unknown (binary does not support --contract-hash; it predates the contract handshake)" — the binary path, and all four remediations including the escape hatch; grep the module's existing find_proxy_bin error for message style). Wire into launch_rust_proxy() between find_proxy_bin() and build_proxy_argv(): if the escape-hatch env var is set to a truthy value, LOG.warning and skip; else check_contract(). Extend kerbside/tests/unit/test_proxy_supervisor.py following its existing mock style: hash-match launches; mismatch raises with both hashes in the message; flag-unsupported (rc!=0) raises with the predates wording; timeout raises; escape hatch launches despite mismatch and logs a warning. tox -epy3 and pre-commit run --files <touched> must pass.
3d Verification, management session: (a) using the step 3b container-built binary (rebuild if the 3a-generated constant changed the proto tree state — it must NOT have), run python3 -c importing proxy_supervisor.get_binary_contract_hash against it and assert equality with contract.CONTRACT_HASH; (b) unzip the 0.4.0 wheel already in the scratchpad (from step 2c) and run check_contract() against its kerbside-proxy binary — expect the RuntimeError with the "predates the contract handshake" wording; (c) with KERBSIDE_SKIP_CONTRACT_CHECK=1, the same call must not raise. Record all three transcripts for the PR description.

Risks and mitigations

  • tox -egenprotos regenerates stubs with unrelated diffs (toolchain drift since the stubs were last committed). Step 3a is instructed to stop and report rather than commit noise; the management session decides whether a stub-refresh commit is warranted separately.
  • Hash divergence from line endings or encoding between sha256sum (3a), sha2 (3b) and hashlib (3c/test): all three hash the same raw file bytes with no text-mode processing, and step 3d(a) proves the Rust and Python values agree on the real artifacts before the phase is called done.
  • The probe adds a subprocess exec to daemon startup: bounded by decision 5's timeout; a hung binary fails the launch loudly (which is correct — it would have hung as the proxy too).
  • Root-owned droppings from the Docker cargo runs: the 3b brief requires a clean git status after; the reviewer (management session) re-checks.
  • A deployer with a legitimately old-but-working pairing is hard-refused after upgrading the Python side only (decision 4 sub-decision): accepted deliberately; the refusal message's remediation list and escape hatch are the mitigation, and phase 4 documents both env vars.

Definition of done

  • kerbside/rpc/contract.py exists, is marked generated, and test_contract.py (which recomputes the hash from the proto bytes) passes — so the constant cannot silently go stale.
  • tox -egenprotos is idempotent on the committed tree (running it changes nothing).
  • The container-built binary's --contract-hash output equals CONTRACT_HASH (step 3d(a) transcript recorded).
  • The 0.4.0 release binary is refused with the predates-the-handshake message, and launches with the escape hatch set (3d(b)/(c) transcripts recorded).
  • cargo fmt --check, cargo clippy --all-targets and cargo test pass in the container; the new Rust test pins the embedded hash's shape.
  • All new supervisor behaviours are unit-tested (match, mismatch, unsupported flag, timeout, escape hatch) and tox -epy3 passes.
  • pre-commit run --all-files passes; git status is clean of Docker droppings.
  • The master plan's Execution table and index.md reflect phase 2 as implemented and phase 3 as planned (done in the planning commit).

Back brief

Before executing any step of this plan, back brief the operator on the plan and how the intended work aligns with it. Gate: if step 3a's tox -egenprotos run surfaces unrelated stub regeneration diffs, pause for the operator before committing anything from that step.